METHODOLOGY FOR BORED CAST IN SITU PILE WITH BENTONITE SLURRY

Image
FLOW CHART FOR PILING WORKS DURING CONSTRUCTION EQUIPMENT AND MATERIALS WE USE FOR PILING WORK EQUIPMENT AND MATERIALS WE USE FOR PILING WORK 1. MAIT HR 130 Piling Rig ( fig.1) Piling Dia.: 500 mm To 1200 mm , Piling Depth : 40 m 2. Hydra Crane (fig. 2) Capacity : 08 to 14 tone 3. Tremie Pipe Set  Diameter: 150 mm Length : 1.0 m To 2.4 m Each pipe 4. Back Hoe Loader  For Excavate Soil And Shifting Of soil 5. Temporary Casing  For Support Earth soil And remove after casting 6. Bentonite Set up  For mixing Bentonite And returning of bentonite METHODOLOGY 1. SETTING OUT: Necessary setting out and survey is to be done for pile points marking. The pile location is set out with respect to the control points by suitable peg marked at location, which shall be checked by client. The permission to start boring will be obtained in standard format as per the checklist. The guide points (min. 3 nos.) are fixed at suitable location outside the casing for future reference and the reference points are